How long does a building permit last. No contractor needed for a shed, just want to build it myself. As money is collected for supplies.

A Google User | Sep 6, 2019 | Category: County government office in Lecanto, Florida

Citrus County Building Division - All questions

Address: 3600 W Sovereign Path # 111, Lecanto, FL 34461, USA

Danny Works | Sep 6, 2019

6 months

Raymond Grosskopf | Sep 6, 2019

The phone number for the Building Dept is 352-527-5310. The best thing is to call and ask questions pertaining to your specific project. A permit is required for a shed. Site plans, engineered building plans etc are needed to make application. Once approved, which could take a few weeks, the permit is issued and valid for 6 months.