How much do they charge when they get to the house to deliver the cement, if we don't have a pump to pumped it and we used the wheelbarrow instead how much is the minutes or hours they stay there ?

gigi tellez | Sep 1, 2019 | Category: Corporate office in San Jose, California

Star Concrete - All questions

Address: 1404 S 7th St, San Jose, CA 95112, USA

Vu Le | Apr 3, 2022

Do you know how much for 1 cubic yard?

Juan Santiago-Vazquez | Sep 1, 2019

They stay there as long as they have to. If you're not ready when they show up on the site they start charging standby time. The give you about 5 minutes per yard and they're suppose to charge you after that but most guys don't. And if you order two yards or less you get a shortload ( or they call it a clean up) you get an extra fee for that too.

Randu Lucachin | Sep 1, 2019

You have 5 minutes per yard then 2 dollars per minute after that